Project:          Branson Medical Mall, Parking Garage and Cahill Road Extension

Location:       Branson, MO

Owner:          Skaggs Community Hospital

Date:             1998 to 2000

PROJECT DESCRIPTION

Palmerton & Parrish, Inc. was retained to provide Geotechnical Services for this multi-million dollar hospital expansion and road extension project. Project includes construction of a three story pre-cast parking garage structure, five story steel frame Medical Mall building and extension of Cahill Road. During the Geotechnical Investigation, use of an ATV drill was required due to steeply sloping wooded terrain. A Geotechnical Investigation was performed which required soil sampling and rock coring for both shallow and deep foundations and for slope stability analysis. Geotechnical aspects of the project included recommendations for both shallow spread footings and drilled piers upon dolomite bedrock, fill placement upon steeply sloping natural hill slope and incorporation of grid reinforcement into fill slopes to increase degree of slope and allow structure support upon the crest of slope.

The Cahill Road Extension required placement of a deep rock fill over localized alluvial deposits. Palmerton & Parrish performed slope stability analyses and recommended staged construction to allow dissipation of pore pressures in natural alluvial deposits below the fill mass. To verify dissipation of pore pressures, Palmerton & Parrish installed pneumatic piezometers. Palmerton & Parrish field personnel were required to monitor piezometer levels to coordinate staged construction.

Palmerton & Parrish was engaged to provide construction testing and inspection during the construction phase of the project. Palmerton & Parrish inspected installation of spread footings and drilled piers to bedrock, installation of Tensar Reinforcing Grid in fill slopes as well as testing of cast-in-place concrete and compacted earth fills. During building erection, Palmerton & Parrish provided fireproof testing and inspection and testing of structural connections. Fillet welds required visual inspection and magnetic particle testing. Moment connection and field splice welds required ultrasonic testing by an ASNT Level II Inspector.

Back to Top


 

Project:         Piezometer and Inclinometer Casing Installation Lock & Dam No. 25

Location:      Winfield, Missouri

Owner:          U.S. Corp of Engineers - St. Louis District

Date:            1995

 

 

PROJECT DESCRIPTION

Lock and Dam No. 25 is a Corp of Engineers Facility near Winfield, Missouri with an operating lock near the Missouri shore and Dam across the Mississippi River. The facility is vital to barge and pleasure boat traffic traveling the waterway. The Corp of Engineers required installation of inclinometer casing at three locations through the Lock Wall socketed approximately 5 feet into bedrock and one piezometer through the Lock Wall. Sampling of alluvium deposits and Standard Penetration Tests (SPTs) were also required at 5 foot intervals. The east Lock Wall is nearly 100 feet from the Missouri Shore and inaccessible to equipment from land. The project also required installation of eight Piezometers through the dam structure 5 feet below the base of concrete and sampling of alluvium deposits to bedrock.

A major challenge of this project was difficult access conditions. Equipment could only be mobilized to drilling locations through hoisting with a crane mounted on a barge platform. Although the drilling depths and hole sizes dictated use of a large size auger drill and mud pump, drilling equipment was limited to smaller weights which could be crane hoisted. For inclinometer installation, a 6-inch diameter bore hole was required through the initial 40 feet of reinforced concrete of the lock wall. For piezometer installation, a 3.75-inch diameter bore hole was required through the 40 feet of lock wall and dam concrete. A 6-inch diameter bore hole was also required through deep alluvium deposits to bedrock at a depth of approximately 120 feet and 5 feet into bedrock. Retrieval of rock core from the bedrock unit was also required at many piezometer and inclinometer locations. Field work required close cooperation between Palmerton & Parrish field personnel and Corp of Engineers operating the lock facility since the lock was in operation throughout the project.

Back to Top


Project:        Motor Transport Operators Course DACA41-92-C-0030 

Location:     Fort Leonard Wood, Missouri

Owner:        United States Army
PROJECT DESCRIPTION

Palmerton & Parrish, Inc. provided services to Willard Quarries, Inc. for purposes of evaluating the aggregates to be used for graded aggregate base, compacted aggregate base and for both intermediate and surface asphalt aggregate. This material will be used in the construction of parking lots and roadway pavements for the Motor Transport Operators Course Construction at Fort Leonard Wood, Missouri. Construction activities included the placement of approximately 80,000 tons of aggregate base material and 80,000 tons of bituminous asphalt pavement.

Laboratory testing was accomplished to evaluate the magnesium sulfate soundness and L.A. Abrasion characteristics of the proposed quarry aggregate. Stockpile gradations and determinations of specific gravities and absorption values were performed during crushing.

Mix designs for both intermediate and surface mixes were prepared by Palmerton & Parrish and the firms providing project testing and control during laydown.

During the progress of the work, Palmerton & Parrish, Inc. personnel have worked closely with Kansas City Corp of Engineer personnel, the Resident Engineer and staff at Fort Leonard Wood and with representatives of the Asphalt Institute.

Back to Top


Project:        Power Generation Peaking Turbines 

Location:      Essex and Maryville, Missouri

Owner:         Associated Electric Cooperative

Date:            Fall of 1998

PROJECT DESCRIPTION

Palmerton & Parrish, Inc. was engaged to perform a Geotechnical Investigation at both sites. One in the Missouri Boothill and the other in Northwest Missouri for these power generation units with heavy compressive loads and significant machine vibrations. Drilling depths ranging from 65 to 85 feet were required within the thick glacial deposits of northern Missouri and deep sand alluvium of the Missouri Boothill. At the Essex site, downhole shear wave testing was also required. Drilling procedures required shelby tube sampling through hollow stem augers as well as performance of Standard Penetration Tests (SPT) in deep sands below the water table while using wash boring procedures. A geologist was also provided to log the borings, collect soil specimens and observe drilling procedures. A geotechnical report was prepared submitting boring logs and alternate recommendations for foundation support. At the Essex site, a pile load test was witnessed to confirm load bearing of the selected pile type. Installation of auger cast piles was inspected by a representative of Palmerton & Parrish during construction.

Back to Top


Project:     Public Affairs Building

Location:  Springfield, Missouri

Owner:      Southwest Missouri State University

Date:         1997

PROJECT DESCRIPTION

Palmerton & Parrish, Inc. provided Geotechnical Services required for this five-story with basement educational facility. The investigation required sampling and analysis of both foundation soils and the shallow bedrock unit for evaluation for both shallow and deep foundation units supporting both basement and non-basement areas. Rock coring of the local Burlington Formation which is a karst limestone was performed to determine suitability of the bedrock for support of drilled piers. A drilled pier foundation system at high end bearing pressure socketed into the competent limestone was selected for support of this major educational structure.

 

Following the Geotechnical Investigation, Palmerton & Parrish, Inc. provided design services for the subsurface drainage system for the basement and connecting tunnel and assisted in determination of appropriate lateral earth pressures for basement and tunnel design. The subsurface drain system incorporated a geomembrane for waterproofing and geosynthetic for subsurface drainage to buried piping. The underdrain system was designed in close cooperation with the Structural and Mechanical Engineers to be compatible with the structural and mechanical systems.

Palmerton & Parrish was engaged as the project Geotechnical Engineer in fielding inquiries from general contractors, piering contractors and excavating contractors bidding the project.

Back to Top


Project:      Stormwater Master Plan for Springfield/Branson Regional Airport

Location:   Springfield, MO

Owner:      City of Springfield, Missouri

Date:         1998

PROJECT DESCRIPTION

Stormwater runoff conditions were modeled for the property controlled by the Springfield/Branson Regional Airport and surrounding properties. The study area consisted of approximately 4,030 acres which was divided into areas that drain to sinkholes (interior drainage areas) and areas that drain by manmade or natural channels to Rainer Branch of Clear Creek in the Sac River Basin. A total of 35 interior drainage areas were identified in this study ranging in size from 0.8 acres to 295.5 acres. The remaining 2,500 acre drainage basin was divided into subbasins and modeled using the US Army Corps of Engineers Flood Hydrograph Package (HEC-1). Flooding conditions were analyzed for the 2, 10, 25 and 100 year storm events for 1972 and 1996 development conditions.

Back to Top


Project:        Skaggs Community Hospital - Hydrocarbon Release Investigation and Remediation 

Location:     Branson, Missouri

Owner:        Skaggs Community Hospital

Date:           1992 to 2000

PROJECT DESCRIPTION

Palmerton & Parrish, Inc. provided environmental services for this project after contaminated groundwater was discovered in piers being drilled for new construction. Environmental services provided for Skaggs Community Hospital included coordination of tank tightness testing for the on-site USTs and subsequent removal of a leaking UST; drilling and sampling program to determine contamination limits; installation of collector wells and monitoring wells; coordination of groundwater clean-up by pump and treat method and preparation of a "Site Characterization Report" and "Corrective Action Plan" for submittal to MDNR. Groundwater clean-up is ongoing at this site.

In addition to the Environmental Investigation, a Geotechnical Investigation and Phase I Environmental Audit were performed for this site. Pier inspection and materials testing services were also provided.

Back to Top


 

e-mail us at: ourhome@ppimo.com

Site Design by Airlink Communications
Best viewed at 800 x 600